Location: Holsworthy Barracks, NSW
Division: Energy
End user: Department of Defence
Client: Department of Defence
Project manager: Ben McDonnell
Contract value: $900,000
Year completed: 2016
Description:
Holsworthy Fill Point (HFP) facility for ground support vehicles
OPEC scope:
OPEC was engaged to design and construct new ground fuel point facility at the Holsworthy Barracks
Challenges/solutions:
This project had particular challenges around the implementation of AS60079 Hazardous Area Classification requirements. OPEC changed the orientation of the tanks to achieve compliance while remaining on the same footprint as originally designed.
Innovations:
OPEC has engineered an innovative modular tank design which saved the client significantly on investment